ICR
Under development
ID: 379

Yenikent Landfill Gas to Electricity Project

Yenikent Landfill Gas to Electricity Project

Please fill out the form to get in touch with the project developers.

Impacts

Project Information

Project Status
Under development
Project Type
Avoidance / Reduction
Sector
Waste handling and disposal
Methodology
ACM0001
Project Description

Yenikent Landfill Gas to Electricity Project (referred to as the “Yenikent LFG” from here on), developed by the ITC-KA Enerji Üretim Sanayi ve Ticaret A.Ş. (hereafter referred to as the “project owner”) is located at the Yenikent landfill site in Ankara Province of Türkiye. The proposed project includes LFG extraction from landfill site and its utilization for power generation. The project activity is operational with a total installed capacity of 15.565 MWe.

Validation Criteria
Applied methodology
Verification Body

Verification Criteria

Media

Location

Country
Turkey
City
Ankara
Address
Gökler District, Gökler Kümeevleri No:237
Geographical Region
N/A
Coordinates
39.94684945490882, 32.47061967984592
View on Map
Credits
All credit information, issuances, retirements and holders.
Est. Annual Mitigations
73K
t CO₂e per year
Est. Total
732K
t CO₂e
Crediting Start Date
MAY 29 '20
Crediting Period
10 Years

Sustainable Developement Goals

Affordable and Clean Energy

Ensure access to affordable, reliable, sustainable and modern energy for all

Decent Work and Economic Growth

Promote sustained, inclusive and sustainable economic growth, full and productive employment and decent work for all

Climate Action

Take urgent action to combat climate change and its impacts

Additionality

Level 1 additionality

Baseline additionality. Compared to the baseline scenario the project needs to mitigate climate change. That is the project must implement actions that are additional to what would occur compared to the baseline.

Level 2a additionality

Statutory additionality. The project must implement actions that are beyond requirements stipulated in local legislation or regulations. Projects are statutory additional if their implementation and/or operation is not required by any law, statute, or other regulatory framework, agreements, settlements, or other legally binding mandates requiring implementation and operation or requiring implementation of similar measures that would result in the same mitigations in the host country.

Level 3 additionality

Technology, institutional, common practice additionality. The project must implement actions that are subject to barriers of implementation or accelerate deployment of technology or activities and carbon market incentives are essential in overcoming these barriers.

Level 4a additionality

Financial additionality I. A project is financially additional if it results in higher costs or relatively lower profitability than would have otherwise occurred in the baseline scenario.

Level 5 additionality

Policy additionality. Implementation of actions may lie out of the scope of the host country's Nationally Determined Contributions under the Paris Agreement and, therefore, not eligible for international transfer mechanism. When project implementation goes beyond its host country’s climate objectives and lies outside of the scope of its climate action strategy towards its NDCs, it is considered to be policy additional.

Participants

An overview of all the people and organizations associated to this project. Participants, validators, verification bodies and other.

Organizations involved in the project

profile picture

ITC-KA Enerji Üretim Sanayi ve Ticaret Anonim Şirketi

Project Owner

Project Proponent

profile picture

4K Earth Science Private Limited

Verification Body

Validation Verification Body

profile picture

Life İklim ve Enerji Ltd. Şti.

Project Developer

Project Developer

profile picture

ITC-KA Enerji Üretim Sanayi ve Ticaret Anonim Şirketi

Project Developer

Project Proponent

People involved in the project

Nazire Gür

Project Participant
profile picture

Ramazan Aslan

Project Participant
profile picture

Emrah Baydun

Project Participant

Stalin S

Auditor
Documents
An overview of all documents connected to this project
Version
File size
ICR Environmental and Socio-economic safeguards

1 documents

Project description

1 documents